Future electricity demand and grid connections of electric road systems for heavy transport

dc.contributor.authorFront, Robin
dc.contributor.authorRaisse, Martin
dc.contributor.departmentChalmers tekniska högskola / Institutionen för rymd-, geo- och miljövetenskapsv
dc.contributor.examinerOdenberger, Mikael
dc.contributor.supervisorTaljegård, Maria
dc.date.accessioned2020-04-29T13:33:57Z
dc.date.available2020-04-29T13:33:57Z
dc.date.issued2020sv
dc.date.submitted2019
dc.description.abstractThis thesis investigates the potential implementation of electric road systems (ERS), a novel technology created with the purpose of electrifying future transport in order to reduce greenhouse gas emissions. Using this technology, electricity is delivered from the electricity grid to the road and further onto the vehicles travelling on the road. This thesis considers the implementation of an ERS for heavy transport such as heavy trucks and buses. More specifically, the purpose of this thesis is to study how the connection points (electrical substations) from an ERS can be placed along the road and how the varying electricity demand from the road will affect the dimensional requirements of the equipment used. This was studied via a case study of the E6 route in Sweden assuming three different vehicle electrification scenarios derived from climate goals as well as electrification trends and statistics: 40%, 70% and 100% electrification. The average and peak electricity demand of the vehicles were calculated using a mathematical model. Three cases of substations placement were assumed; the first case was based on a previous proposition from the report Slide-in Electric Road System where the electrical substations are placed with a 40 km distance between each other, the second case was based on assuming there is available capacity in existing substations and connecting the ERS to these, the third case was based on the geographical load distribution of the ERS by making an investment cost optimization based on cost of cables and substation equipment. This was done assuming all substations were dimensioned by the same power and the optimization model was created to find out the optimal substation dimension, balancing the number of substations and their investment cost against the cost of the cables connected to the road between the stations. It can be concluded that if spare capacity in existing substations is sufficient it would obviously be the least cost alternative to use these substations. However, data regarding existing capacity is classified making it difficult to draw any conclusions. But generally the grid strength is weaker in southern parts of route E6 where demand is high and production is low, possibly making current substations unsuitable. Therefore, if additional substation capacity is required a cost optimization will lead to best return of investment. The substation dimensions for the three scenarios based on the cost optimization were 45 MWfor the 40% scenario and 48MWfor both the 70% and the 100% scenario, for route E6. At larger dimensions, the cable costs are increasing rapidly while the investment cost of the substations are low. As the cables make up most of the total cost, the solution is defined by the balance of cable versus substation cost at these dimensions. Another conclusion is that the expected peak electricity demand is a large factor when dimensioning the substations, as traffic during peak hours can be 3-4 times higher than the average yearly traffic. If usage of the ERS during the worst peak hours can be avoided, large dimensioning requirements can be cut and the investment costs can be reduced by a considerable amount. For the cases with low electrification, the model resulted in few substations along route E6, making the distance between stations very long which can have negative effects related to voltage drop and power losses.sv
dc.identifier.coursecodeSEEX30sv
dc.identifier.urihttps://hdl.handle.net/20.500.12380/300769
dc.language.isoengsv
dc.setspec.uppsokLifeEarthScience
dc.subjectElectric road systemsv
dc.subjectERSsv
dc.subjectElectricity gridsv
dc.subjectElectrical substationssv
dc.subjectRamp-upsv
dc.subjectClimate targetsv
dc.subjectCost optimizationsv
dc.titleFuture electricity demand and grid connections of electric road systems for heavy transportsv
dc.type.degreeExamensarbete för masterexamensv
dc.type.uppsokH
local.programmeSustainable energy systems (MPSES), MSc
Ladda ner
Original bundle
Visar 1 - 1 av 1
Hämtar...
Bild (thumbnail)
Namn:
Exjobbsrapport_RobinMartin_200405_FINAL.pdf
Storlek:
2.79 MB
Format:
Adobe Portable Document Format
Beskrivning:
License bundle
Visar 1 - 1 av 1
Hämtar...
Bild (thumbnail)
Namn:
license.txt
Storlek:
1.14 KB
Format:
Item-specific license agreed upon to submission
Beskrivning: