Information Needs and Barriers in the Construction Reuse Market; Developing a Framework for Information Structuring
Hämtar...
Publicerad
Författare
Typ
Examensarbete för masterexamen
Master's Thesis
Master's Thesis
Modellbyggare
Tidskriftstitel
ISSN
Volymtitel
Utgivare
Sammanfattning
The construction industry is one of the largest contributors to waste and greenhouse
gas emissions, making the transition towards circular strategies such as material
reuse increasingly important. However, the implementation of reuse in Swedish
construction projects remains underdeveloped, in part due to the lack of standardized
information structures and workflows for reused materials. This study investigates
the information needs of key actors in the Swedish construction industry to enable
efficient handling of reused construction materials in digitalized projects. A qualitative
approach was adopted, combining a literature review, a semi-structured interview
study with 16 participants across 14 interviews, and a case study of the Kaj 16 project
in Gothenburg. The findings confirm that contractors, reuse suppliers, designers and
clients each have distinct information needs that must be met at different stages and
points in time. Several barriers were identified as hindering efficient information flows,
including inconsistent inventory practices, the absence of mandatory information
criteria on reuse platforms, late involvement of key actors, and a fragmented market
structure based on informal networks. Based on the empirical findings and identified
barriers, a supplier information framework is proposed, structured around four process
stages: inventory, condition assessment, market communication and integration. The
framework specifies minimum information requirements per stage, distinguishes
between baseline and complex element requirements, assigns role responsibility and
emphasizes timing as a critical dimension. The study concludes that the primary
challenge for digitalization of reuse processes is adoption rather than technological
availability, and that establishing clear information expectations at the procurement
stage is essential for enabling more structured and systematic reuse in Swedish
construction.
Beskrivning
Ämne/nyckelord
reuse, Swedish construction, information Management, digitalization, reuse market, standardization, logistics, circularity.